Kenya Power New Connection: Cost, Documents and How Long It Takes

Kenyan woman on a phone call while working on a laptop – kenya power new connection cost
Kenyan woman on a phone call while working on a laptop. Photo: Queen Asali / CC BY-SA 4.0 via Wikimedia Commons

“How much to connect my home?” gets the same answer every time: there is no fixed price. Here is the process Kenya Power describes.

Based on questions customers sent to Kenya Power’s official customer-care X account (@KenyaPower_Care) and Kenya Power’s own replies, checked on 14 October 2026. Questions are paraphrased.

How to apply

Apply on the Kenya Power Self-Service Portal (selfservice.kplc.co.ke) using the Enquiry for Supply of Electricity form, attaching a copy of your national ID, KRA PIN certificate, land ownership document and a route sketch map.

Cost

Kenya Power says the cost is not fixed: after you apply, its team assesses the site and issues a personalised quotation. There is “no estimated cost at this stage” before the assessment. We will not quote a figure.

Kenyatta Avenue in Nairobi with KICC in view – illustrating kenya power new connection cost
Kenyatta Avenue in Nairobi with KICC in view. Photo: Bahnfrend / CC BY-SA 4.0 via Wikimedia Commons

Timelines Kenya Power gives

  • Quotation, meter only: about 7 days.
  • Quotation needing network extension or a transformer: 14–28 days.
  • Installation after paying the quotation: generally 14–21 working days.

Kenya Power adds that timelines depend on site requirements and that you can track progress on the MyPower app.

Last Mile and prepaid switches

Kenya Power says it cannot confirm Last Mile availability for an area remotely – visit the nearest KPLC office. To switch from postpaid to prepaid, visit a Kenya Power office with your ID and account details.

Frequently asked questions

How much does a Kenya Power connection cost?

There is no fixed price; Kenya Power issues a quotation after a site assessment.

How long does a new connection take?

Kenya Power says quotation takes about 7 days (meter only) or 14–28 days (extension/transformer), and installation 14–21 working days after payment.

What documents do I need?

National ID, KRA PIN certificate, land ownership document and a route sketch map.

Related: Kenya Power help hub · Tokens not received · Why you get fewer units

About Author

Norah Waceke is a business journalist and editor at Business Radar with more than eight years of experience covering Kenya's economy, companies and markets. She previously worked at Kenyans.co.ke, one of the country's leading digital news platforms, where she reported on business, finance and current affairs. A graduate of Multimedia University of Kenya, Norah focuses on clear, accurate reporting that helps readers understand the money stories shaping their lives and businesses.

More from Norah Waceke · Editorial policy

Related stories

Kenya Power electricity substation – kenya power tokens not received
Energy

Kenya Power Tokens Not Received? How to Retrieve Them (*977#) and What “USED” Means

Delayed or missing token SMS is one of the most common questions to Kenya Power on X. Based on questions
Young Kenyan woman talking on her mobile phone – kenya power fewer units
Energy

Why Do I Get Fewer Kenya Power Units? Tariff Bands, Last Mile and Rebilling Debts

“Why did my units drop?” is the second big token question. Kenya Power’s replies point to three causes. Based on